Off site materials
It can sometimes be appropriate for the client to pay for items even though they remain ‘off-site’, for example, where a contractor has themselves made a large payment for plant or materials that have yet to be delivered to site, or if the client wishes to ‘reserve’ key items in order to protect the programme. Such items should be agreed in advance and listed in an annex to the contract bills.
Paying for off-site goods or materials can be useful, however, it does put the client at risk, for example if the contractor becomes insolvent and the items are then not delivered, even though payment has been made.
Several mechanisms are available to protect the client:
- The client should check the financial status of the contractor to assess the likelihood of insolvency.
- The client should require proof that the property in the items is vested in the contractor before payment is made. This may include a vesting certificate (certifying that property has passed to the contractor and that the materials will be properly identified, stored and insured), and checking that the suppliers terms and conditions do not include a retention of title clause.
- The items should be set aside, and clearly marked with the client’s details.
- The materials should be 'ready for incorporation'.
- The client should require proof that the materials are insured against specified perils for the period they remain off site.
- If the contractor is part of a larger group, then a guarantee might be required from the holding company.
- An on-demand bond might be required up to the value of the off-site items, with the value of the bond reducing as deliveries to site are made.
- The client might enter into a contract direct with the supplier.
However, none of these methods is fool proof. For example, a vesting certificate may be of limited value in practice, as it is difficult to sue an insolvent contractor. Furthermore, despite best endeavours, items may simply be removed or disappear in the event of insolvency, or if there is a rumour that insolvency might occur. This is particularly true for items that have yet to be fabricated, items that have still to be worked on, or items that are abroad.
In a perfect world, items would be delivered to the site and affixed to the property before payment is made, but where this is not possible, a judgement is necessary to assess the risk to the project, or the potential loss to the client versus the cost of ensuring absolute certainty in relation to off-site goods.
See also: Materials on site.
For legal issues, see Off-site goods and materials - legal issues.
[edit] Related articles on Designing Buildings
- Advance payment bond.
- Bonds and guarantees.
- BSRIA launches Offsite Construction for Building Services topic guide.
- Construction inventory management.
- Design for Manufacture and Assembly (DfMA).
- How to make projects off-site ready.
- Just in time manufacturing.
- Lead time.
- Logistics management.
- Long lead-time item.
- Materials.
- Materials on site.
- Off-site construction.
- Off-site goods and materials - legal issues.
- Off site, on track.
- On site.
- Platform approach to design for manufacture and assembly.
- Precast.
- Precast flat panel system.
- Protecting and storing rebar.
- Retention of title.
- Site storage.
- Vesting certificate.
Featured articles and news
CIOB photographic competition final images revealed
Art of Building produces stunning images for another year.
Major overhaul of planning committees proposed by government
Planning decisions set to be fast-tracked to tackle the housing crisis.
Strategic restructure to transform industry competence
EBSSA becomes part of a new industry competence structure.
Industry Competence Steering Group restructure
ICSG transitions to the Industry Competence Committee (ICC) under the Building Safety Regulator (BSR).
Principal Contractor Competency Certification Scheme
CIOB PCCCS competence framework for Principal Contractors.
The CIAT Principal Designer register
Issues explained via a series of FAQs.
Conservation in the age of the fourth (digital) industrial revolution.
Shaping the future of heritage
Embracing the evolution of economic thinking.
Ministers to unleash biggest building boom in half a century
50 major infrastructure projects, 5 billion for housing and 1.5 million homes.
RIBA Principal Designer Practice Note published
With key descriptions, best practice examples and FAQs, with supporting template resources.
Electrical businesses brace for project delays in 2025
BEB survey reveals over half worried about impact of delays.
Accelerating the remediation of buildings with unsafe cladding in England
The government publishes its Remediation Acceleration Plan.
Airtightness in raised access plenum floors
New testing guidance from BSRIA out now.
Picking up the hard hat on site or not
Common factors preventing workers using head protection and how to solve them.
Building trust with customers through endorsed trades
Commitment to quality demonstrated through government endorsed scheme.
New guidance for preparing structural submissions for Gateways 2 and 3
Published by the The Institution of Structural Engineers.
CIOB launches global mental health survey
To address the silent mental health crisis in construction.
Key takeaways from the BSRIA Briefing 2024
Not just waiting for Net Zero, but driving it.
Comments
To start a discussion about this article, click 'Add a comment' above and add your thoughts to this discussion page.