Off site materials
It can sometimes be appropriate for the client to pay for items even though they remain ‘off-site’, for example, where a contractor has themselves made a large payment for plant or materials that have yet to be delivered to site, or if the client wishes to ‘reserve’ key items in order to protect the programme. Such items should be agreed in advance and listed in an annex to the contract bills.
Paying for off-site goods or materials can be useful, however, it does put the client at risk, for example if the contractor becomes insolvent and the items are then not delivered, even though payment has been made.
Several mechanisms are available to protect the client:
- The client should check the financial status of the contractor to assess the likelihood of insolvency.
- The client should require proof that the property in the items is vested in the contractor before payment is made. This may include a vesting certificate (certifying that property has passed to the contractor and that the materials will be properly identified, stored and insured), and checking that the suppliers terms and conditions do not include a retention of title clause.
- The items should be set aside, and clearly marked with the client’s details.
- The materials should be 'ready for incorporation'.
- The client should require proof that the materials are insured against specified perils for the period they remain off site.
- If the contractor is part of a larger group, then a guarantee might be required from the holding company.
- An on-demand bond might be required up to the value of the off-site items, with the value of the bond reducing as deliveries to site are made.
- The client might enter into a contract direct with the supplier.
However, none of these methods is fool proof. For example, a vesting certificate may be of limited value in practice, as it is difficult to sue an insolvent contractor. Furthermore, despite best endeavours, items may simply be removed or disappear in the event of insolvency, or if there is a rumour that insolvency might occur. This is particularly true for items that have yet to be fabricated, items that have still to be worked on, or items that are abroad.
In a perfect world, items would be delivered to the site and affixed to the property before payment is made, but where this is not possible, a judgement is necessary to assess the risk to the project, or the potential loss to the client versus the cost of ensuring absolute certainty in relation to off-site goods.
See also: Materials on site.
For legal issues, see Off-site goods and materials - legal issues.
[edit] Related articles on Designing Buildings
- Advance payment bond.
- Bonds and guarantees.
- BSRIA launches Offsite Construction for Building Services topic guide.
- Construction inventory management.
- Design for Manufacture and Assembly (DfMA).
- How to make projects off-site ready.
- Just in time manufacturing.
- Lead time.
- Logistics management.
- Long lead-time item.
- Materials.
- Materials on site.
- Off-site construction.
- Off-site goods and materials - legal issues.
- Off site, on track.
- On site.
- Platform approach to design for manufacture and assembly.
- Precast.
- Precast flat panel system.
- Protecting and storing rebar.
- Retention of title.
- Site storage.
- Vesting certificate.
Featured articles and news
BSRIA Statutory Compliance Inspection Checklist
BG80/2025 now significantly updated to include requirements related to important changes in legislation.
Shortlist for the 2025 Roofscape Design Awards
Talent and innovation showcase announcement from the trussed rafter industry.
OpenUSD possibilities: Look before you leap
Being ready for the OpenUSD solutions set to transform architecture and design.
Global Asbestos Awareness Week 2025
Highlighting the continuing threat to trades persons.
Retrofit of Buildings, a CIOB Technical Publication
Now available in Arabic and Chinese aswell as English.
The context, schemes, standards, roles and relevance of the Building Safety Act.
Retrofit 25 – What's Stopping Us?
Exhibition Opens at The Building Centre.
Types of work to existing buildings
A simple circular economy wiki breakdown with further links.
A threat to the creativity that makes London special.
How can digital twins boost profitability within construction?
The smart construction dashboard, as-built data and site changes forming an accurate digital twin.
Unlocking surplus public defence land and more to speed up the delivery of housing.
The Planning and Infrastructure Bill
An outline of the bill with a mix of reactions on potential impacts from IHBC, CIEEM, CIC, ACE and EIC.
Farnborough College Unveils its Half-house for Sustainable Construction Training.
Spring Statement 2025 with reactions from industry
Confirming previously announced funding, and welfare changes amid adjusted growth forecast.
Scottish Government responds to Grenfell report
As fund for unsafe cladding assessments is launched.
CLC and BSR process map for HRB approvals
One of the initial outputs of their weekly BSR meetings.
Building Safety Levy technical consultation response
Details of the planned levy now due in 2026.
Great British Energy install solar on school and NHS sites
200 schools and 200 NHS sites to get solar systems, as first project of the newly formed government initiative.
600 million for 60,000 more skilled construction workers
Announced by Treasury ahead of the Spring Statement.
Comments
To start a discussion about this article, click 'Add a comment' above and add your thoughts to this discussion page.